300kt/a PA Project for INDORAMA ICS in Senegal

100m2 Rotary Table Vacuum Filter for 300kt/a PA

Project Overview

Key Challenges:

• Second overseas retrofit project involving complete filtration system (including pumps, piping, and separators)
• Required installation of larger equipment (replacing existing 77m² filter) to meet client’s capacity expansion needs
• First overseas self-installation project with strict quality supervision by French engineering inspectors

Our Solutions:
• Deployed multi-disciplinary team (process/technical/equipment engineers) for on-site assessment
• Developed innovative elevated installation solution
• Conducted targeted civil structure reinforcement
• Implemented two-shift work schedule with local workforce coordination

Client Feedback:

The 72-hour continuous operation test demonstrated outstanding performance:

  • Achieved a daily throughput of 562 tons, exceeding the required 558 tons/24h specification
  • Maintained gypsum water-soluble phosphorus content at 0.47, surpassing the 0.5 target requirement

For more project details, feel free to contact us.

Share To:

Поделиться на facebook
Поделиться на twitter
Поделиться на linkedin

поиск

Связанные проекты

300kt/a Phase 1&2&3 PA Project for Guizhou LuFa Industry Co., Ltd.
300kt/a Phase 1&2&3 PA Project for Guizhou LuFa Industry Co., Ltd.
Yunnan Evergreen Chemical Co
200kt/a MAP Project for Yunnan Evergreen Chemical Co., Ltd.
Qinghai Chuangxin Mining Development Co., Ltd.
50kt/a PA and 100kt/a Powdered MAP Project for Qinghai Chuangxin Mining Development Co., Ltd.
ru_RURussian

Спасибо за ваше сообщение!

Мы получили вашу информацию и скоро свяжемся с вами.